Hi Siva,
The above note worked thanks a lot, awarded full points.
But I have got error in phase MAIN_SHDINST/SUBMOD_SHDALIASCRE/SCEXEC_GRA_ORG!
Last error code set: 1 processes failed, check 'SCEXEC_G.*' for details
When checked the SCEXEC_G.001 log says :
hnpclecd:ecdadm 81> cat SCEXEC_G.001
SAPup> Starting subprocess with PID 11501 in phase 'SCEXEC_GRA_ORG' at
20140414114523
ENV: DIR_LIBRARY=/sapdump/SUM/SUM/abap/bin
ENV:
LD_LIBRARY_PATH=/sapdump/SUM/SUM/abap/bin:/sapdump/SUM/SUM/jvm/jre/lib/am
d64/server:/sapdump/SUM/SUM/jvm/jre/lib/amd64:/sapdump/SUM/SUM/jvm/jre/..
/lib/amd64:/usr/sap/ECD/SYS/global/syb/linuxx86_64/sybodbc:/sybase/ECD/AS
E-15_0/lib:/sybase/ECD/OCS-15_0/lib:/sybase/ECD/OCS-
15_0/lib3p64:/sybase/ECD/OCS-
15_0/lib3p:/usr/sap/ECD/SYS/exe/run:/usr/sap/ECD/SYS/exe/uc/linuxx86_64
ENV: PATH=/sapdump/SUM/SUM/abap/bin:/sybase/ECD/ASE-
15_0/jobscheduler/bin:/sybase/ECD/ASE-15_0/bin:/sybase/ECD/ASE-
15_0/install:/sybase/ECD/DBISQL/bin:/sybase/ECD/OCS-
15_0/bin:/usr/lib64/qt-
3.3/bin:/usr/local/bin:/bin:/usr/bin:/usr/sap/ECD/SYS/exe/uc/linuxx86_64:
/usr/sap/ECD/SYS/exe/run:/home/ecdadm:.
ENV: SAPSYSTEMNAME=ECD
ENV: dbms_type=syb
ENV: dbs_syb_dbname=ECD
ENV: dbs_syb_port=4901
ENV: dbs_syb_schema=SAPSR3
ENV: dbs_syb_server=hnpclecd
EXECUTING /sapdump/SUM/SUM/abap/bin/SAPuptool execdb ../var/PTALORGR.XQLLogging to '/sapdump/SUM/SUM/abap/log/PTALORGR.LOG'
FATAL ERROR: DBSL error 99: Connect failed
[ASE Error SQL30274:08S01]Error setting up connection
SAPup> Process with PID 11501 terminated with status 20 at
20140414114529!
Any idea ?
Regards,
Srikanth G